Hidden losses calculator: what the stops nobody records really cost

Hidden losses are the minutes a machine spends stopped or running slow without leaving a record: micro-stops, waits, and short adjustments. They don't show up in any report, but they take up capacity you're already paying for. This calculator estimates how many hours they add up to per year, what they're worth, and what it's worth to bring your OEE to target.

By the MTSolutions teamUpdated:

Estimate your hidden losses

What downtime means in a company and why part of it stays hidden

Downtime is all the time a machine was supposed to produce and didn't. On the plant floor it's also called a stop, a stoppage, or an outage. Part of it is visible and gets recorded: the two-hour failure, the changeover, the power outage. Another part leaves no trace, for three reasons:

  • It's too short. A micro-stop lasts seconds or a couple of minutes. The operator clears it and keeps going. Writing it down would take longer than fixing it.
  • It doesn't look like a stop. If the machine runs slower than its ideal cycle, it is running. Nobody counts it as downtime, but at the end of the shift there are units missing.
  • The standard gets recorded, not the reality. The changeover "takes 30 minutes" in the report even if it took 50.

That second part is what this calculator estimates. For the full classification of downtime in production, read what downtime is and how to detect it.

How it is calculated

  • Unrecorded hours per year = machines × shifts per day × days per week × weeks per year × unrecorded minutes ÷ 60.
  • Annual value = unrecorded hours × value of one machine hour.
  • Hidden OEE points per shift = unrecorded minutes ÷ (hours per shift × 60) × 100.
  • Recoverable hours = machines × shifts × hours per shift × days × weeks × (target OEE − current OEE).
  • Value of reaching the target = recoverable hours × value of one machine hour.

These are two independent calculations. The first puts a value only on the minutes nobody records. The second puts a value on the entire gap between your current OEE and your target, which includes hidden losses as well as known losses. Don't add them together.

Worked example

A plant with 10 machines runs 2 shifts of 8 hours, 5 days a week, 48 weeks a year. In each shift, each machine loses 20 minutes to short stops nobody writes down. One machine hour is worth USD 150.

  1. Unrecorded hours: 10 × 2 × 5 × 48 × 20 ÷ 60 = 1,600 hours per year.
  2. Value: 1,600 × USD 150 = USD 240,000 per year.
  3. Hidden OEE points: 20 ÷ 480 × 100 = 4.2 points per shift.
  4. If OEE goes from 65% to 75%: 10 × 2 × 8 × 5 × 48 × 0.10 = 3,840 recoverable hours, worth USD 576,000 per year.

To put it in perspective: each machine in this plant has 3,840 planned hours per year. The 1,600 unrecorded hours are equal to 41.7% of one machine's annual capacity. Twenty minutes per shift doesn't sound like much. Multiplied by 4,800 machine shifts a year, it stops being small.

How to estimate unrecorded minutes before you measure

The most uncertain input in the calculator is the unrecorded minutes. There is a way to approximate it with information you already have: compare what the machine produced with what it should have produced during the time it is shown as running.

  1. Take a normal shift. Write down the planned time and the stops that did get recorded.
  2. Subtract: that is the time when, according to the record, the machine was producing.
  3. Calculate the theoretical output for that time using the ideal cycle.
  4. Compare it with actual output. The difference, converted to minutes, is the time that doesn't appear in any report.

Example: a 480-minute shift with 40 minutes of recorded stops. According to the record, the machine produced for 440 minutes. Its ideal cycle is 3 seconds per unit, or 20 units per minute: it should have delivered 8,800 units. It delivered 8,400. That leaves 400 units missing, which at 20 per minute is 20 minutes. Those 20 minutes went to micro-stops and reduced speed.

Repeat the calculation for five to ten shifts on different machines and use the average. Two warnings. If the ideal cycle you use is the historical average and not the design cycle, the difference will come out close to zero even though the loss exists. And if you want to see the loss with your own eyes, count one machine's micro-stops for an hour with a stopwatch: the number usually surprises the person who runs it every day.

How to estimate the value of one machine hour

It is not the accounting cost of the machine. It is what you earn, or stop spending, if that hour is recovered. It depends on the line's situation:

SituationWhat the recovered hour is worthExampleHourly value
Bottleneck with demandThe contribution margin on the extra units you produce and sell600 units per hour × USD 0.25 margin per unitUSD 150
The backlog is covered with overtimeThe cost of the overtime and the utilities you stop paying for3 operators × USD 14 per overtime hour + USD 18 in energy and utilitiesUSD 60
No additional demandOnly the variable cost you avoid by finishing earlier2 operators × USD 9 per hour + USD 7 in energyUSD 25

The figures in the example are illustrative: use your own. With the same 1,600 hours, the result ranges from USD 240,000 per year in the first case to USD 96,000 in the second and USD 40,000 in the third. That's why it pays to agree on the hourly value with finance before you show the result: it is the assumption that gets challenged the most.

Contribution margin is the selling price minus the unit's variable costs (raw material, packaging, energy). Don't subtract fixed costs: you pay them whether you produce or not.

Sensitivity: what happens with 10, 20, and 30 minutes

Because the minutes are an assumption, present a range and not a single number. With the plant in the example and USD 150 per hour:

Unrecorded minutes per shiftHours per yearAnnual valueHidden OEE points
10800USD 120,0002.1
201,600USD 240,0004.2
302,400USD 360,0006.3

The result is proportional: each additional minute per shift and per machine adds 80 hours and USD 12,000 per year in this plant. Even the low scenario, 10 minutes, is a figure that justifies measuring. That is the conclusion that holds up when the assumption gets challenged.

Where the losses hide

LossWhy it isn't recordedWhat it looks like with automatic measurement
Micro-stopsThey last less than the time it takes to write them downDozens of short stops per shift, each with its exact time
Reduced speedThe machine is running, so nobody counts it as a lossLow performance against the ideal cycle
Startups and changeoversThe standard time is written down, not the actual timeActual duration of each changeover, by shift and by crew
Waiting for material or peopleNobody clearly owns themStops classified by cause
Causes logged as "other"The list of causes doesn't match what actually happensA cause tree tailored to the line

The machine downtime that does get recorded has an owner and a plan. The downtime that falls into this table has neither, and that's why it repeats every shift.

How to present the number to management

  • Show the range. "Between USD 120,000 and USD 360,000 per year, depending on the assumption" is more credible than an exact figure nobody can back up.
  • Put the assumptions on the first slide. Minutes per shift, hourly value, number of machines. Anyone who wants to argue with the result will argue with an assumption, and that's exactly what you want.
  • Translate it into capacity. 1,600 hours are 41.7% of one machine's annual capacity. For someone weighing whether to buy equipment or add a shift, that fact carries more weight than the dollar amount.
  • Keep the two results separate. The value of the hidden losses and the value of reaching your target OEE answer different questions. Don't add them up.
  • Don't call it savings. It is capacity that isn't being used today. It turns into money only if you sell more or spend less.
  • Ask for a small decision. Don't ask for the budget for the whole plant. Ask to measure one line and come back with the real data.

From the calculation to the plan: the first 30 days

  1. Days 1 to 5: choose one line. The one that is the bottleneck or the one that generates the most overtime. Validate the ideal cycle of its main products with maintenance and with the manufacturer.
  2. Days 6 to 12: measure a sample by hand. Apply the actual-versus-theoretical output method to ten shifts and time the micro-stops for one hour per shift. You'll have a first value of your own to replace the 20 minutes in the example.
  3. Days 13 to 20: classify. Together with the operator, put together a short list of causes for the short stops: jam, material shortage, adjustment, cleaning. Ten causes are enough to get started.
  4. Days 21 to 25: go after one cause. The one that repeats the most. A single action, with an owner and a date.
  5. Days 26 to 30: recalculate and decide. Come back to this calculator with your own data. If the number holds up, you already have the case for measuring automatically and continuously.

Manual measurement works for this first month. It doesn't hold up over time: it depends on someone stopping production to write things down.

What this estimate doesn't tell you

  • The unrecorded minutes are an assumption. Before measuring with machine data, almost nobody knows their real value.
  • Not every recovered hour turns into sales: it depends on demand and on where the bottleneck is.
  • It doesn't include the cost of quality or the cost of late deliveries.
  • It assumes every machine loses the same amount. In practice, a few machines account for most of the loss.

How to go from the estimate to real data

MTcontrol records every stop from the machine signal, including the short ones, and the operator enters the cause in 2 clicks. That way the minutes that are an assumption today become a data point by machine and by shift. With Ultimate AI, anyone on the team can ask a question in your language and get the cause, the data, and the next step.

The model is designed so that you don't carry the risk of the estimate. Installation takes as little as 1 hour per machine and the hardware is on loan at no cost: you don't buy equipment. It typically takes about 6 weeks from the first visit to the Proof of Count, and we only start billing once the data matches your reality. You can leave with 30 days' notice. We have spent 17 years in the market doing this on the plant floor.

If you want to calculate the OEE of a shift with your own numbers, use the OEE calculator. To separate failures from the rest of your stops, use the MTTR and MTBF calculator.

Real case: Degasa

Degasa, a manufacturer of healthcare supplies, invested USD 16,038 and achieved savings of USD 4,634 per month on a single line. It recovered its investment in 3 and a half months, on a single line. Across the whole plant, in the first year of implementation, the savings came to USD 210,000. Before measuring, those losses weren't in any report. If you'd like to see more customer results or talk about your plant, reach us through contact.

Other calculators

Frequently asked questions

What are hidden losses?

They are the minutes when a machine is stopped or running slower than it should without any record being kept: micro-stops, waits, short adjustments, and reduced speed. They don't appear in stop reports, but they do appear in the difference between what the line produced and what it should have produced.

What does downtime mean in a company?

It is the time when a piece of equipment or a line was supposed to produce and didn't: failures, changeovers, waiting for material, lack of staff, and micro-stops. It is measured in minutes and valued by the production that didn't get made during that time.

What are micro-stops?

They are very short stops, lasting seconds or a few minutes, that the operator clears without calling maintenance: a jam, a dirty sensor, a fallen container. Each one seems irrelevant, but they repeat dozens of times per shift and almost never get written down. In OEE they show up as low performance.

How do I know how many minutes I'm losing without recording them?

Without automatic measurement, it's an estimate. Compare a shift's actual output with what would have come out at the ideal cycle during the time the machine is shown as running. The difference in units, converted to minutes, is the unrecorded time. Repeat it across several shifts.

What machine-hour value should I use?

If the line is a bottleneck and there is demand, the contribution margin it generates in an hour. If you cover backlogs with overtime, the cost of those hours. If there is no additional demand, only the variable cost you avoid. Agree on the value with finance.

How do you calculate the cost of machine downtime?

Multiply the hours stopped by the value of one machine hour. For a year: machines times shifts times days times weeks times minutes lost in each shift, divided by 60, and then times the hourly value. With 10 machines and 20 minutes per shift, the example on this page comes to 1,600 hours.

Can I add the value of the hidden losses to the value of the OEE target?

No. They are two different calculations. The first puts a value only on the unrecorded minutes. The second puts a value on the entire gap between your current OEE and the target, which already includes part of those hidden losses. If you add them, you count the same hours twice.

Is the result exact?

No. It is a reference estimate that depends on your assumptions, above all the unrecorded minutes and the hourly value. It helps you size the problem and decide whether measuring is worth it, not commit to a result. Present it as a range.

Is the calculator free? What happens with my data?

It's free. To show the result we ask for your name, email, and phone number, and we use them to contact you about your result in accordance with our Privacy Policy. The numbers you enter in the calculator are sent along with the request.

Ask your plant